Thursday, 28 July 2011
Monday, 18 July 2011
Horizontal Stabiliser - Drilling Horizontal Stabiliser Left Hand Side (3.2 Hrs)
Today I
-Finally pilot drilled the fwd flanges on HS405
-Drilled all rib to spar holes to #30 size except the HS708
-Unclecoed, Deburred holes & Re-Clecoed
-Clecoed skin on
-Enlarged HS708 holes to #21
-Slipped HS704 & 5 in place and marked holes
-Removed and fluted HS405/5
-Marked Centreline on HS404/5 flange
-Aligned flange centreline with holes and clamped in place
-Drilled aft flange of HS405 to HS603
-Drilled HS609pp to Skin attach holes
-Drilled HS405-702-710 and HS405-714-704 holes
Match drilled all remaining holes in Skin
-Finally pilot drilled the fwd flanges on HS405
-Drilled all rib to spar holes to #30 size except the HS708
-Unclecoed, Deburred holes & Re-Clecoed
-Clecoed skin on
-Enlarged HS708 holes to #21
-Slipped HS704 & 5 in place and marked holes
-Removed and fluted HS405/5
-Marked Centreline on HS404/5 flange
-Aligned flange centreline with holes and clamped in place
-Drilled aft flange of HS405 to HS603
-Drilled HS609pp to Skin attach holes
-Drilled HS405-702-710 and HS405-714-704 holes
Match drilled all remaining holes in Skin
Saturday, 16 July 2011
Horizontal Stabiliser - Drilling Horizontal Stabiliser (1.2 Hrs)
Continued to try to figure out drilling of HS404/5 but decided to leave this and get more info.
-Removed skins off skeleton
-Removed skins off skeleton
Friday, 15 July 2011
Horizontal Stabiliser - Drilling Horizontal Stabiliser (1.75 Hrs)
-I spent ages trying to work out the HS405 FWD Flange Drilling in Sec D-D but decided to leave that & assemble the HS temporarily with clecos to get an idea of how the assembly fits together.
Horizontal Stabiliser - Rib Preparation (.25 Hrs)
-I fluted the HS708 R, HS706 L&R & HS707 L&R.
As we dont know the location of holes on HS404 & 405 I wont flute them yet
As we dont know the location of holes on HS404 & 405 I wont flute them yet
Horizontal Stabiliser - Rear Spar Assy (0.75 Hrs)
The primer is now dry on the VA146 bearing so I riveted the HS411's around the Bearing with a -5 rivet for the first rivet, but like many other builders I wasn't happy with the shop head so I drilled it out and did all the rivets with -6.
-Next I clecoed the hs411 assembly to the spar & enlarged the attachment holes to #12 size.
-I then marked the parts
-Next I clecoed the hs411 assembly to the spar & enlarged the attachment holes to #12 size.
-I then marked the parts
Thursday, 14 July 2011
Horizontal Stabiliser - Rear Spar Assy (0.8 Hrs)
Today I
-Received my new HS411BPP & HS411APP Brackets so I clecoed them to the Aft HS spar with the VA146 Bearing sandwiched between them & drilled four of the holes through to the HS411APP as only the HS411BPP is punched with the holes for the hinge bearing
-I then removed the assembly & drilled the remaining two holes
-Next I deburred the parts and primed the VA146 bearing with Tempo Zinc Phosphate Self Etching Primer.
Bearing Assy. Clecoed Ready to Drill |
Bearing Assy. Removed to Drill Remaining Two Holes |
Bearing Masked Ready to Prime |
Priming Bearing |
Bearing Primed |
Wednesday, 6 July 2011
Horizontal Stabiliser - Rib Preparation (1 Hr)
Today I
-Notched the aft end of both HS404 ribs as per "HS404 Trim Detail" Drawing 3
-Got a reply from Van's letting me know that my HS702 Front Spar is fine, and i don't need to replace it
-Notched the aft end of both HS404 ribs as per "HS404 Trim Detail" Drawing 3
-Got a reply from Van's letting me know that my HS702 Front Spar is fine, and i don't need to replace it
Monday, 4 July 2011
Horizontal Stabiliser - Fwd Spar Assy (2.2 Hrs)
Today I
-Trimmed the IB ends of 2nd HS702 as per "front spar tab detail" drawing 3
-Marked bend line and cut relief notch on HS702 #2
-I found some deep scratching at the relief notch on HS702 #1 so I have blended them out and emailed vans with measurements and photos
-While I wait for the results from vans I'll build on and redo HS702 #1 If need be.
-Bent tabs on HS 702 #1&2 as per view B-B drawing 3
-Countersunk centre four holes on HS710 & 714 & dimpled centre four holes on HS702.
-Trimmed the IB ends of 2nd HS702 as per "front spar tab detail" drawing 3
-Marked bend line and cut relief notch on HS702 #2
-I found some deep scratching at the relief notch on HS702 #1 so I have blended them out and emailed vans with measurements and photos
-While I wait for the results from vans I'll build on and redo HS702 #1 If need be.
-Bent tabs on HS 702 #1&2 as per view B-B drawing 3
-Countersunk centre four holes on HS710 & 714 & dimpled centre four holes on HS702.
Relief Notches |
Bends Complete |
First Dimples |
First Countersinks |
Sunday, 3 July 2011
Horizontal Stabiliser - Fwd Spar Assy (1.7 Hrs)
Monday, 27 June 2011
Horizontal Stabiliser - Fwd Spar Assy (1.3 Hrs)
Today I
-Clecoed HS710 (reinforcement angle) & HS714 (splice angle) to HS702 (fwd spar channels)
-Match drilled holes inboard of HS404/5 rib attach points
-Tapered the ends of HS714 as per drawing 3
-Clecoed HS710 (reinforcement angle) & HS714 (splice angle) to HS702 (fwd spar channels)
-Match drilled holes inboard of HS404/5 rib attach points
-Tapered the ends of HS714 as per drawing 3
Sunday, 26 June 2011
Horizontal Stabiliser - Rear Spar Assy (2.7 Hrs)
Today I smoothed the edges and faces of the HS609PP bars.
-There was a bit of scratching in one of them, but i was able to sand them out.-Next I clecoed the stiffener bars to the spar channel and final drilled all the holes.
-I then enlarged the HS708 attachment holes to #21 size.
-Then I clecoed HS412/413 brackets to spar channel and match drilled them with a #30 drill.
-Next I match drilled the HS411APP through the HS411BPP but i wasn't happy with the alignment of the holes so i scrapped them and have ordered new ones from Van's.
Smoothed Edges and Faces of HS609PP |
Friday, 17 June 2011
Horizontal Stabiliser - Rear Spar Assy (0.4 Hrs)
Today I:
*Broke The edges of both HS609PP bars
*Checked bend of spar channel (HS603PP) in relation to HS609PP
*Rounded the ends of HS-609PP Bars
*Broke The edges of both HS609PP bars
*Checked bend of spar channel (HS603PP) in relation to HS609PP
*Rounded the ends of HS-609PP Bars
Thursday, 16 June 2011
Practise Kit
-Today i finished my second practise kit (the control surface piece) now i'm ready to start the empennage.
Sunday, 8 May 2011
Wednesday, 13 April 2011
Ordering Tools
-Today I ordered my tool kit from Isham Inc., I ordered the AirVenture FULL RV Tool Kit
Monday, 11 April 2011
Ordering
-Today I faxed away the order forms & sent the money to Van's in the US, The Empennage is in stock, so it will come first via FedEx Air Mail, then the Fuselage, Wings & Finishing kits will come when they are in stock via sea mail.